Power Grid Corporation Leads in India's FY28 Transmission Pipeline Execution
A PL Capital research note highlights a growing disparity in execution readiness within the power transmission sector in India. State-owned Power Grid Corporation of India demonstrates a decisive edge over Adani Energy Solutions, particularly in the near-term project maturity and execution for the fiscal year 2028. Both entities show comfortable visibility for project commissioning in FY27.
Power Grid's FY27 portfolio, valued at ₹33,100 crore, is in an advanced stage, with 95% of foundations completed and 85% of towers erected. For FY28, Power Grid is managing a ₹75,200 crore commissioning slate, based on Central Electricity Authority projections, with 67% of foundations and 50% of towers already completed. A substantial portion, ₹51,800 crore, is slated for commissioning in the first quarter of FY28, providing an "execution cushion."
In contrast, Adani Energy Solutions' FY27 lineup of ₹12,300 crore is on track, with 89% of foundations completed and 82% of equipment received. However, its ₹12,600 crore pipeline for FY28 is in early development, with only 17% of foundations laid and 4% of towers erected as of July 2026. This indicates that Adani Energy Solutions will require a greater execution ramp-up to meet its scheduled rollout. The overall market share for private developers has increased to 46% from 43%, supported by ₹1,21,200 crore in tariff-based competitive bidding projects.