IHI and Polish Firms Win Early Contracts for Lubiatowo-Kopalino AP1000
IHI Secures Containment and CA01 Scope
IHI has been contracted to supply two critical components for the first AP1000 unit at the Lubiatowo-Kopalino nuclear power plant in northern Poland. The scope covers the reactor containment vessel, which encloses the reactor and associated safety systems, and the CA01 super module — a concrete and steel assembly composed of 47 sub-modules measuring more than 26 metres long, 29 metres wide, and 23 metres high. Positioned inside the containment module, the CA01 houses the reactor pressure vessel, steam generators, and related equipment.
The award follows authorisation granted last month by Polskie Elektrownie Jądrowe (PEJ) for Westinghouse to begin procuring long-lead items for the first unit. PEJ confirmed that the initial order scope encompasses six key components of the nuclear island, including the containment vessel and associated structural modules.
Conditional Orders Placed with Polish Suppliers
Westinghouse has subsequently issued conditional purchase orders to four Polish companies for additional structural modules within the AP1000 containment building. Mostostal Kielce SA has been assigned the CA02 Walls Module Scope, while Mostostal Krakow SA will supply the CA05 Walls Module Scope. Energomontaż-Północ Gdynia SA (EPG) holds the CA03 Module Scope, and FAMAK SA is responsible for the CA20 Floors Module Scope.
Within the AP1000 design, the CA02 and CA03 modules form part of the in-containment refuelling water storage tank. The CA05 module provides reinforced steel plate walls that separate rooms inside the containment building, while the CA20 module consists of reinforced concrete slabs on steel plates forming the floors of a larger assembly that houses plant equipment.
The current scope of work for all suppliers includes preparing technical documentation, quality and supervision plans, supplier selection and contracting, and initiating material procurement. Manufacture and delivery of finished components to the construction site will be addressed under a subsequent order that PEJ intends to issue as part of the main plant construction contract.
Modular Construction and Schedule Context
The AP1000 design relies on modular construction, with large prefabricated steel-concrete structural and mechanical modules fabricated off-site and installed during construction. Early procurement of long-lead components is standard practice in nuclear projects to secure manufacturing capacity and reduce schedule risk.
Three AP1000 units are planned for the Lubiatowo-Kopalino site in the Choczewo municipality in Pomerania. Construction is scheduled to begin in 2028. Under a recent revision to Poland's nuclear power programme, the first unit is now targeted for commercial operation in 2036, with the plant reaching full capacity in 2038 — three years later than previously planned.