Initial fuel loading completed at San'ao unit 2
China General Nuclear (CGN) completed initial fuel loading at San'ao unit 2 on 2 November, advancing the Hualong One reactor toward nuclear-powered commissioning. The operation transferred 177 fuel assemblies from the spent fuel pool's fuel racks into the reactor core using semi-automatic refuelling equipment.
CGN described the process: after operators completed the fuel loading sequence programming, the programme was imported into the refuelling machine's control system, with specialised fuel operators then directing the sequential transfer. The operation also employed a floating light gun independently developed by CGN to provide underwater illumination of the core, which the company said helped ensure the smooth progress of the loading process.
Project timeline
The San'ao plant received State Council approval for its first phase — units 1 and 2 — in September 2020. China's National Nuclear Safety Administration issued a construction permit for both units on 30 December 2020, with first concrete for unit 1 poured the following day. First concrete for unit 2 followed on 30 December 2021.
Unit 1 achieved first criticality in February 2026 and was connected to the grid in March, before being declared commercially operational on 29 April. Unit 2 completed cold functional tests in October 2025 and hot functional tests in April 2026. Commercial electricity supply from unit 2 is scheduled for 2027.
Expanding capacity
San'ao is the first nuclear power project in China's Yangtze River Delta region to adopt the Hualong One reactor design. Units 3 and 4, also Hualong One reactors, were among 11 reactors approved by China's State Council in August 2024; first concrete for the unit 3 nuclear island was poured on 19 December 2025. A further two Hualong One units are planned as units 5 and 6 at the same site.
Upon full completion, the plant is projected to supply more than 54 TWh of electricity annually to Zhejiang Province and the broader Yangtze River Delta region, while reducing standard coal consumption by more than 16 million tonnes and cutting carbon dioxide emissions by more than 51 million tonnes per year, according to CGN.
Ownership structure
San'ao represents the first Chinese nuclear power project to involve private capital. Geely Technology Group holds a 2% stake in the project company, Cangnan Nuclear Power. CGN is the majority shareholder with 46%, and other state-owned enterprises hold the remaining shares.