Copenhagen Atomics and Urenco Partner on UF4 Deconversion Facility
Agreement Overview
Copenhagen Atomics and Urenco have entered into an agreement under which Urenco will support the design of a dedicated facility to deconvert uranium hexafluoride (UF6) into uranium tetrafluoride (UF4). The new production line will be integrated into Copenhagen Atomics' existing fuel facility in Copenhagen.
Under the arrangement, Copenhagen Atomics will source enriched UF6, convert it to UF4 on-site, and use the material to synthesise high-purity fuel salts. The salts are intended both for the company's own reactors and for supply to other molten salt reactor (MSR) developers and research institutions.
Supply Chain Significance
Copenhagen Atomics describes the UF4 production line as the concluding element of its in-house fuel supply chain, enabling what it characterises as tonne-scale fuel-salt production — a capability it claims is the first of its kind globally. The company's CTO, Aslak Stubsgaard, stated that establishing the line in Copenhagen provides the final missing piece needed for full in-house production of reactor-ready fuel salts.
Iain Roche, Business Development Director at Urenco, described the collaboration as bringing together complementary capabilities to develop a novel fuel solution and build the supply chain required for its future deployment.
Separately, Copenhagen Atomics has also purchased low-enriched uranium (LEU) from Urenco for use in its first reactors.
Reactor Technology Context
Copenhagen Atomics is developing a containerised molten salt reactor moderated with unpressurised heavy water. The design is intended to consume nuclear waste while breeding new fuel from thorium, with a thermal output of 100 MWt. The company is targeting mass manufacturing and assembly-line production methods, with a stated levelised cost of energy goal of EUR 20 (approximately USD 22.4) per MWh.
UF4 is a required input for thorium-fuelled MSRs as a kick-starter fuel, and also serves as the base fuel for other MSR designs. The deconversion line therefore supports both Copenhagen Atomics' own programme and the broader advanced reactor sector.
The company's first nuclear test reactor is expected to operate at the Paul Scherrer Institute in Switzerland, with commercial deployment targeted for the early 2030s.
Broader Sector Activity
The agreement follows Urenco's recent signing of a memorandum of understanding with MSR developer Thorizon, which is examining Urenco's potential role in the molten salt fuel supply chain and the possible use of depleted uranium — a byproduct of enrichment operations — as a fuel resource for advanced reactors.