Posiva Initiates Deposition Hole Drilling at Onkalo Repository
Drilling Operations Underway
Posiva has begun drilling the first deposition hole at the Onkalo repository in the Olkiluoto bedrock, more than 400 meters below the surface. The operation commenced after a safety and technical review meeting. The Deposition Hole Boring Machine (DHBM), manufactured by Herrenknecht AG, was delivered to the Onkalo site in June 2022. This machine, weighing 78 tonnes, is over 9 meters long, 3 meters wide, and nearly 4 meters tall. The drilling complex also includes a 7-meter, 22-tonne energy unit and an 18.5-tonne drill processing plant.
Prior to this, Herrenknecht AG's crew conducted test drilling of four holes in late 2022, followed by Posiva's crew drilling an additional four test holes with supplier assistance. The current deposition hole is being drilled vertically into the floor of an excavated final disposal tunnel. Upon completion, it will be 8.4 meters deep and 1.75 meters in diameter. A strict tolerance of 25 millimeters deviation from the vertical centerline is enforced along the entire length of the hole. The first three holes will undergo additional measurements upon completion to ensure compliance. If the deviation exceeds the permitted limit, the hole will be rejected for final disposal.
Repository Development and Future Plans
Kimmo Lehtola, Posiva's Construction Manager for Operations, stated that drilling an 8-meter hole at Onkalo typically takes about ten hours of effective drilling time. The objective is to achieve a production rate of approximately two finished deposition holes per working week once the process is fully integrated into normal operations. The first final disposal tunnel, approximately 330 meters long, is designed to accommodate around 30 drilled deposition holes.
The Onkalo repository, located near the Olkiluoto nuclear power plant, was selected in 2000. Posiva, jointly owned by Fortum and Teollisuuden Voima Oyj (TVO), submitted its construction license application in December 2013, which was granted in November 2015. Construction began a year later. In July 2022, Posiva announced the completion of excavation for the first five disposal tunnels, totaling about 1700 meters. Over the 100-year operational period, an estimated 100 deposition tunnels, with a total length of approximately 35 kilometers, will be excavated. Posiva submitted its operating license application for the encapsulation plant and final disposal facility in December 2021, seeking approval for operations from March 2024 to the end of 2070. The Radiation and Nuclear Safety Authority (STUK) has indicated that safety requirements for the operating license have been met, with a government decision anticipated in the autumn. Posiva's President and CEO, Ilkka Poikolainen, aims for operational readiness by the end of 2026.