Holtec Submits Preliminary Safety Analysis Report for Palisades SMRs
Holtec has submitted the Preliminary Safety Analysis Report (PSAR) to the US Nuclear Regulatory Commission (NRC) for its Pioneer 1 & 2 SMR-300 units. This submission completes the second phase of the Construction Permit Application (CPA) process, which was initiated with the Limited Work Authorization (LWA) application and Environmental Report (ER) in December 2025.
The PSAR provides the NRC with detailed technical and safety information to support Holtec's application to construct two SMR-300 small modular reactors at the Palisades site in Covert Township, Michigan. These units, Pioneer 1 & 2, are designed to add 680 MW of generating capacity and will be located adjacent to the existing 805 MWe Palisades nuclear power plant. The twin-unit Pioneer plant will become part of the Palisades Energy Campus.
Regulatory Milestones and Technical Advancements
The PSAR submission follows several pre-submittal engagement meetings and technical interactions with NRC staff. Recent milestones in the SMR program include:
Holtec is also working with the NRC to review an issue where a single fuel assembly did not load as planned at the Palisades plant, which is currently in the final stages of fuel loading.
- A novel civil construction method utilizing shop-fabricated modules, validated through testing at Purdue University, aims to reduce labor requirements compared to conventional construction. The associated Licensing Topical Report (LTR) was audited and accepted by the NRC in September 2026, with the Safety Evaluation Report (SER) expected by early November 2026.
- An LTR defining a methodology for predicting soil-structure interaction (SSI) effects under various seismic and soil conditions was audited and accepted by the NRC in September 2026. The SER for this LTR is anticipated by the end of October 2026. This methodology is intended to support the deployment of a standard SMR-300 design across diverse global sites.
- An LTR detailing an innovative instrumentation and control architecture was audited and accepted by the NRC in August 2026, with official regulatory approval expected in October 2026.
- The NRC's draft SER for the LWA application, representing the first phase of the CPA, is anticipated in December 2026. The NRC audit for this application concluded in September 2026.
Next Steps
Upcoming development tasks include completing a Class 2 construction estimate, developing a 4D simulation of the entire plant to visualize the construction process, and finalizing confirmatory safety analyses for the plant's Final Safety Analysis Report (FSAR).