EPC Talks Collapse for Czech Dukovany New-Build; CEZ to Relaunch Procurement
Negotiations Break Down After Prolonged Talks
Korea Hydro & Nuclear Power (KHNP) has ended construction contract negotiations with a consortium led by Daewoo Engineering & Construction for the $18.6 billion (€16.5 billion) project to build two APR1000 reactors at the Dukovany site in the Czech Republic. KHNP stated that the two parties were unable to reach agreement on key contract terms despite an extended negotiation period.
According to the consortium, the immediate trigger was a set of revised contract terms submitted by KHNP on 7 October 2026, which gave the consortium approximately three weeks to review the proposed changes. Reports from South Korea indicated that the broader breakdown followed more than a year of discussions over construction costs and the allocation of financial responsibility for design modifications.
Industry sources said KHNP had demanded a reduction of more than 10% from the consortium's original bid price, a cut equivalent to over $750 million. The consortium, which includes Doosan Enerbility alongside Daewoo E&C, called for negotiations to resume following the breakdown.
CEZ Moves to Terminate Cooperation Agreement
Czech state-controlled utility CEZ announced on 28 October 2026 that it would move to terminate its cooperation agreement with the Daewoo-led consortium and initiate a new bidding process to identify a replacement EPC contractor. The decision represents a significant procurement reset for a project that had already reached an advanced contracting stage.
The Dukovany project involves two large-scale APR1000 units to be built at the existing Dukovany nuclear power station in the southern Czech Republic, located approximately 50 kilometres from the Austrian border. A government-backed intergovernmental deal between Czech nuclear project company EDU II and KHNP was signed in June 2025. Daewoo E&C and Doosan Enerbility had been selected as construction partners in 2018 and participated in the original bidding process.
KHNP vice-president and head of project operations Choi Il-kyung was quoted by The Korea Herald as playing down the risk of major disruption to the overall project timeline, though no further detail on a revised procurement schedule was provided in available statements.
Supply-Chain Implications
The collapse of EPC talks introduces material uncertainty into the construction supply chain for one of Europe's largest planned nuclear new-build programmes. With CEZ now required to run a fresh contractor selection process, the timeline for mobilising civil and mechanical works at Dukovany is likely to face revision. The scale of the cost dispute — centred on who bears the financial burden of design changes — may also influence how future EPC packages for APR1000 projects are structured elsewhere.