NTPC Ltd. has terminated a ₹413.37 crore contract awarded to GR Infraprojects Ltd. (GRIL) for a 400 MWh Battery Energy Storage System (BESS) project at its Mouda Super Thermal Power Station. The decision was made due to GRIL's failure to meet contractual obligations and required project progress. The contract, initially awarded in March 2026, was scheduled for completion within 15 months.
Significant delays in critical activities were observed, and GRIL did not implement necessary corrective measures after NTPC issued a contractual notice. Following the termination, NTPC has encashed approximately ₹91 crore in available securities, in line with contractual provisions. The company has initiated the process to re-tender the project at the risk and cost of GRIL, prioritizing early re-award and timely implementation.
The Mouda BESS project is crucial for enhancing grid flexibility and integrating renewable energy, supporting NTPC's broader strategy for deploying battery energy storage alongside its conventional generation assets. NTPC aims to ensure the timely execution of the project as energy storage becomes increasingly vital for balancing a power system with growing renewable energy components.