Changjiang Unit 4 Completes Cold Functional Tests, Advancing Towards Commissioning
Cold Functional Tests Conclude for Changjiang Unit 4
Changjiang Unit 4, a Hualong One reactor, has successfully completed its cold functional tests. This milestone signifies the unit's official entry into the commissioning phase, paving the way for subsequent hot testing, fuel loading, and eventual grid connection. Cold functional tests are designed to confirm the proper installation and operational readiness of safety-critical components and systems under cold conditions. These tests involve operating reactor systems in conjunction with auxiliary systems for the first time.
The primary objective of these tests is to verify the leak-tightness of the primary circuit and its components, including pressure vessels, pipelines, and valves within both the nuclear and conventional islands. The process also includes cleaning the main circulation pipes. During the tests, the primary loop system's pressure was progressively increased through several stages, reaching a maximum of 22.3 MPa, with systematic assessments conducted at each pressure level.
Project Overview and Site Development
Two Hualong One reactors, Changjiang units 3 and 4, are under construction as part of the second phase of the Changjiang plant. First concrete for Unit 3's nuclear island base slab was poured in March 2021, followed by Unit 4 in December of the same year. The total estimated investment for Changjiang Phase II is CNY40 billion (USD5.9 billion).
Changjiang Unit 3 achieved first criticality on July 10 and was connected to the grid on August 1. Both units are projected to be fully operational by early 2027. The Changjiang nuclear site currently operates two CNP-600 pressurized water reactors, Changjiang 1 and 2, which began commercial operation in 2015 and 2016, respectively.
In addition to the Hualong One units, construction began in 2021 on a demonstration ACP100 small modular reactor at the Changjiang site. This multi-purpose 125 MWe pressurized water reactor, also known as the Linglong One, is designed for various applications including electricity generation, heating, steam production, and seawater desalination. It is currently undergoing pre-commissioning tests. Hainan Province's energy policies, published in 2019, designate nuclear power as the primary electricity source for the island.